|
1. |
The FloorCut the Floor Frame members (skids and joists) from
the
'Materials List', to the measurements shown in
the
'Skid and Joist Outlay'
plan. On level ground,
make up the Floor Frame, also as per the
'Skid and Joist Outlay'
plan.
Cover the floor with 20mm (3/4) inch plywood,
nailing a maximum of 200 (8") apart on all joists.
Alternative flooring can be used such as 20mm (3/4")
thick boards, or other suitable sheet. |
|
2. |
The Wall
FramesCut the Wall Frame members from the
'Materials List' to the measurements as shown in
the
'Wall Frame and Stud Placement' and Cross Section
Plans. Cut the longest members first.
Make the Wall Frames up on even ground, referring to
the
'Wall Frame and Stud Placement' Plan which shows
the placement of the studs from a bird's eye-view.
In this particular plan, the Studs are spaced at 600
[2ft] crs or o.c.(which means "at centers" or "on
center"). This means the Studs are spaced apart 600
(2ft) from the center of one Stud, to the center of
the adjoining Stud (where possible).
Studs spaced at 600 [2ft] crs/o.c. are also placed
appropriately to accommodate standard width 1200
[4ft] Cladding or Lining, either exterior and
interior. |
|
3. |
Wall Frame
Nogging
Fix four rows of Noggings, evenly spaced between all
the Studs. This is best done while the Wall Frame is
still laid on the ground. The Noggings give the
exterior vertical Boards something substantial to be
nailed to. |
|
4. |
Lift and
Fix the Wall Frames in Place
Nail the Wall Frames together at the corners so the
outside edges of the corner Studs are flush.
Ensure the Bottom Plate is straight and that the
outside edge is flush with the edge of the floor and
then nail in place. Make the walls plumb (vertical)
and temporarily brace on the inside of the walls. |
|
5. |
The Roof
BeamCut and fix the two Beam Supports on top of (and in
the middle of) the front and rear Wall Frame Top
Plates. The Roof Beam can then be cut to length and
fixed in place on top of the two Beam Supports.
Cut four end rafters as per the
'Rafter Detail'
drawing and fix in place. Plumb
and temporarily brace.
Page 5: Instructions 2
|
6. |
The Roof
Rafters
Cut the remaining eight intermediate rafters (see
'Rafter Detail'
drawing) and fix in place, four
each side. Spacings are shown in
'The Roof Plan'. |
|
7. |
Roof
Noggings
Measure and cut four rows of Noggings that will fit
between the Rafters. Place the rows each side of the
Side Wall's top plates (see Picture). This is so the
exterior Boards and Battens will have a straight
edge at the top to butt into.
The same applies to any likely interior lining,
should you choose to use it. |
|
8. |
Roof
Sheathing
Cover the floor with 12mm (1/2) inch plywood,
nailing a maximum of 200 (8") apart on all Rafters.
Run the sheets from the Roof Beam to the ends of the
Rafters. The sheets will need trimming.
All joins running parallel with the Rafters, must be
on a Rafter. Any necessary join running parallel
with the Roof Beam, must be under a Purlin. |
|
9. |
The
Purlins
Nail three rows of Purlins to each plane (side) of
the roof, overhanging each side of the gables by
25mm (1") or the thickness of the exterior vertical
Boards.
Fix the top row about 75 (3") down from the apex
(this measurement will depend upon the width of the
Ridge Capping, as the Ridge Capping is fixed to the
top purlin), the bottom row vertically flush with
the end of the Rafter and another row in the middle.
Nail the ends of the Roof Sheathing (from the
underside) to the bottom purlins.
|
|
10. |
Fascia,
Barge and Roof Underlay
Nail the Barge Board to the end of the Purlins up
along each rake of the gable and flush with the top
of the Purlins.
Join the Barge Boards at the apex (vertical cut) and
cut the other (lower) end vertically, 175mm (6")
past the rafter (lower) ends.
Cut and fix the fascia Board in between the Barge
Boards and to the Rafter ends. The top edge of the
Fascia Board should be flush with the top of the
bottom Purlin.
Cover the roof with a self-supporting Underlay prior
to the Corrugated Roofing Iron going on. |
Page 6: Instructions 3
|
11. |
The RoofFix the Roofing Iron to the Purlins with appropriate
roofing nails/screws. Fix to the top and bottom
Purlins at every second corrugation and fix to the
intermediate Purlins at every 3rd or 4th
corrugation. Fix through the high side of the
corrugation.
Overhang the roofing approx 65 (2 1/2") past the
Fascia Board or 50 (2") past the back of the gutter.
|
|
12. |
Ridge
Capping and Barge FlashingStandard Ridge Capping is about 130 (5") each side
of the apex, but can vary and any size can be made
to order. Have the Ridge Flashing in mind when
positioning the top Purlin. Fix to the Purlin at
every second corrugation.
The Barge Flashing goes under the Ridge Capping at
the top. Fix to each purlin (through two
corrugations) and also to the barge board. |
|
13. |
Cladding UnderlayA Cladding Underlay should envelop the exterior
walls prior to the cladding being fixed.
|
|
|
14. |
Exterior
Vertical BoardsCommence fixing the Boards to the Wall Frames,
beginning from one corner. Cut the Boards long
enough so that they will touch the underside of the
Rafter at the top and run at least 50mm (2") below
the floor.
Nail the Boards to the Noggings with nails
approximately 75mm (3") apart (including the nail
that will be going through the Batten). Leave a gap
between each board.
|
|
15. |
The
BattensFix the Battens 75x25 (1x3) over each join.
Preferably, the battens should have a groove each
side of the join to stop water being drawn up by
capillary action.
Nail on the center line of the Batten, through the
gap between the Boards and into the Noggings.
Overlap on corners (see picture). |
|
16. |
Done!Install the Door, install the Window and you're
done! |
|
No comments:
Post a Comment